Southern Area Harbour in Ust-Luga Operable

  • The newly built water basin of the Southern Area in the port of Ust-Luga has been put into operation by order of RF Federal Agency for Maritime and River Transport (Rosmorrechflot), the Agency said in a statement.

    The construction lasted from September 2008 till December 2019, the federal budget invested into the project more than 2 bn rubles ($33.2 mn).

    The Southern Harbour consists of four areas with a total area of 73.9 hectares providing access for vessels to the multifunctional terminal, the timber terminal, and the auxiliary fleet base currently under construction.

    Photo: Rosmorrechflot


  • Leave a Reply

    Related content
    18.01.2022
    The construction of a third track on the Slyudyanka 1 – Slyudyanka 2 section […]
    20.09.2022
    Far East and Arctic development Corporation and RZD Logistics have signed an agreement on […]
    22.08.2022
    SPM-1 and SPM-2 temporarily out of service
    07.11.2022
    Okhotsk Commercial Port Ltd has received the status of a resident of the Nikolaevsk […]
    25.07.2022
    Vostochnaya Stevedoring Company has put into operation a new vehicle entrance gate facility, the […]
    20.04.2022
    The ro-ro/lo-lo ferry “Ursa Major” is joining the service between Ust-Luga in Leningrad Oblast […]
  • Login
  • No Fields Found.