New Grain Berth in Azov Port

  • The Main Department of State Expertise has approved project documentation and engineering survey results for a project to build a new berth in Azov Sea Port.

    The new Berth 28 is to be built under the federal Sea Ports Development project. At present, the grain terminal of Azov Sea Port consists of four berths No 29, 30, 31 and 32 with a total quay length of 649.2 m and an annual capacity of 6.7 mn tons.

    The capacity of the new berth will be up to 1.7 mn tons per annum. The 130,9 m long berth will adjoin Berth 29 thus expanding the overall quay length to 780.1 m and increasing the terminal capacity to 8.4 mn tons per annum. Later, after Berth 27 is expanded, the terminal capacity will further increase to make 10.2 mn tons per annum.

    Berth 28 project area occupies 2.6 ha, the operation water basin will cover 2.5 ha. In addition to berth construction, the project envisages building a vessel loading facility, a control checkpoint, utility and administrative buildings, etc.


  • Leave a Reply

    Related content
    17.06.2022
    United Grain Company and Primorsk Universal Handling Complex signed an agreement on cooperation at […]
    06.12.2022
    Ruscon, part pf Delo Group, made a test shipment of linseeds in containers to […]
    03.08.2022
    In July 2022, Russia’s deep-sea Black Sea ports handled more than 953.6 thousand tons […]
    08.08.2022
    The RF Ministry of Agriculture can amend the grain export target for the current […]
    13.07.2022
    Berth N4 used for handling liquefied petroleum gas at the Taman Handling Complex in […]
    08.12.2022
    RN-Vankor, the upstream division of Rosneft, has completed building a berth on the Yenissei […]
  • Login
  • No Fields Found.