Mammoet получил крупный контракт по проекту «Артик СПГ 2»

Mammoet Signs Arctic LNG 2 Contract

  • Heavy lifting specialist Mammoet has been contracted to provide unloading, transportation and installation services for Novatek’ Arctic LNG 2 project. The company has been engaged by the Technip-led joint venture NovArtic.

    According to Mammoet, the company will carry out over half a million tons of lifting operations in the Gydan peninsula during four years.

    Mammoet is to install 42 large modules onto three concrete gravity-based structures (GBS) in Murmansk. The project is expected to use a total of around 2,000 SPMT axles, several Mega Jack lifting systems, a crane fleet spearheaded by a CC8800-1 crane that comes complete with a Boom Booster, and also around 120 workers at peak times.

    This is the biggest-ever contract in the history of Mammoet, in terms of the overall tonnage. Each module will weigh between 8,000 and 17,000 tons; over the project’s lifespan the total weight of lifting operations will reach some 500,000 tons.

    Mammoet will provide unloading, lifting, jacking and skidding services at the purpose-built shipyard near Murmansk, ensuring a continuous installation of the modules on top of the GBS.


  • Leave a Reply

    Related content
    13.08.2020
    Global Ports Investments has relocated 6 E-RTG cranes manufactured by Konecranes its from Ust-Luga Container […]
    08.07.2020
    Rosatomflot, the operator of Russia’s nuclear icebreaker fleet, has extended the recourse of the […]
    05.10.2020
    On October 3, the newly built nuclear icebreaker “Arktika” reached the North Pole, United […]
    08.12.2020
    A shuttle tanker has been laid down at the Zvezda Shipbuilding Complex, Rosneft reports. […]
    01.09.2020
    Novatek Gas & Power Asia Pte. Ltd., a wholly owned subsidiary of Russia’s gas […]
    02.12.2020
    Roll Group, a specialized MPP carrier, enters the Russian market by signing an agency […]
  • Login
  • No Fields Found.