Крупнотоннажное оборудование для комплекса АмКар идет по Москве-реке

Heavylift Equipment for AmKar Shipped by River

  • Delivery of high and heavy equipment for a new plant of AmKar that will produce 525 thousand tons of ammonia and 700 thousand tons of carbamide per annum in Shchekino is underway.

    The equipment is shipped by sea and is transshipped onto inland vessels at the Bronka terminal in St. Petersburg. From there, the cargo is carried by rivers and canals to the construction site.

    At present, two heavylift pieces of equipment, namely, a 270-ton carbon dioxide absorber and a 160-ton low and high pressure evaporator are being shipped by the Moscow Canal, the Moscow River and the Oka Rive.

    The aggregates were delivered to Bronka in late October last year and were stored at the terminal till the start of inland navigation season.

    One of these days they are expected to arrive to the village of Bynyrevo, from where they will be carried to the construction site overland.


  • Leave a Reply

    Related content
    23.08.2022
    FESCO Transport Group has launched a seasonal service branded FESCO Amur River Bridge (FARB) […]
    20.09.2022
    Far East and Arctic development Corporation and RZD Logistics have signed an agreement on […]
    16.11.2022
    November 15, the navigation season of 2022 was over in the Volga-Baltic Waterway basin […]
    21.02.2022
    An electric engine for the main gas booster compressor of the Sakhalin-2 onshore processing […]
    17.01.2022
    According to the Statistics Finland, freight traffic by the Saimaa Canal amounted to 1.23 […]
    31.10.2022
    International logistics operator Ahlers has put into operation the first phase of its fifth […]
  • Login
  • No Fields Found.