Tender to Complete Pionersky Port Project

  • Rosmorport has announced a tender to continue and complete the construction of the international sea port in Pionersky in Kaliningrad region.

    The project envisages building two berths with a total length of 725 m for cargo vessels and cruise liners, and a 110 m berth for port fleet, as well as coastal engineering structures, shore-based infrastructure and the terminal building.

    Initially, Rosmorport awarded the contract to Bolwerk, but terminated the contract in 2019 as the construction process that started in 2018 slowed down and was altogether suspended. 

    The project capacity of the would-be terminal is 305 thousand passengers and up to 80 thousand tons of cargo per annum.


  • Leave a Reply

    Related content
    05.10.2021
    October 1 a new transport and logistics center was inaugurated at the rail station […]
    07.07.2021
    A multimodal transport and logistics hub is to be developed in Sverdlovsk region according […]
    11.10.2021
    Russia’s Black Sea city of Sochi is planning to resume a ferry connection with […]
    09.04.2021
    Transit container transportation between China and Europe via Kaliningrad Railway grew 10-fold during Q1, […]
    25.05.2021
    The dual fuel rail and car/truck ferry “Ivan Shernyakhovsky” under construction for Russia’s port […]
    27.10.2021
    FESCO Transportation Group has signed a new five-year contract with India’s NCPOR for providing […]
  • Login
  • No Fields Found.