Tender to Complete Pionersky Port Project

  • Rosmorport has announced a tender to continue and complete the construction of the international sea port in Pionersky in Kaliningrad region.

    The project envisages building two berths with a total length of 725 m for cargo vessels and cruise liners, and a 110 m berth for port fleet, as well as coastal engineering structures, shore-based infrastructure and the terminal building.

    Initially, Rosmorport awarded the contract to Bolwerk, but terminated the contract in 2019 as the construction process that started in 2018 slowed down and was altogether suspended. 

    The project capacity of the would-be terminal is 305 thousand passengers and up to 80 thousand tons of cargo per annum.


  • Leave a Reply

    Related content
    30.06.2021
    A new tank far is to be built on the territory of the condensed […]
    07.07.2021
    A multimodal transport and logistics hub is to be developed in Sverdlovsk region according […]
    11.03.2021
    DB Cargo in cooperation with Mann Lines Multimodal have launched the first block train […]
    19.04.2021
    The Main Department of State Expertize has approved the project and cost estimate documentation […]
    07.04.2021
    The construction of Russia’s first international cableway across the Amur River between Blagoveschensk in […]
    08.06.2021
    United Grain Company, Russia-‘s governmental port property management agency Rosmorport and Demetra Holding uniting […]
  • Login
  • No Fields Found.