На Волго-Каспийском морском судоходном канале начались дноуглубительные работы

Dredging in Volga-Caspian Canal Starts Ahead of Schedule

  • Dredging in the Volga-Caspian Shipping Canal started on March 28, earlier than planned, the RF Federal Agency for Maritime and River Transport has reported.

    The first dredger to start operations in the Canal was the hopper dredger “Pyotr Sablin”, to be joined by nine more units by April 1. A total of up to 18 dredger groups are to be deployed in the Volga-Caspian Shipping Canal this year.

    The target dredging volume for the season of 2023 is 12 mn cubic meters, more than twice as much as last year, which also saw a record-breaking amount of soil extracted.

    The aim is to increase the depth in the canal so as to make it possible doe vessels with a draft of 4.5 meters to pass.


  • Leave a Reply

    Related content
    07.03.2023
    Rosmorport, Russia’s federal agency responsible for port infrastructure in federal property, has commenced maintenance […]
    15.03.2023
    The dredging season in the in the Volga-Caspian Shipping Canal is to start as […]
    27.02.2023
    The Main Department of State Expertise has approved of the design estimates for the […]
    26.06.2023
    Maintenance dredging has been completed in the basin of Shakhtersk sea port on the […]
  • Login
  • No Fields Found.