В Темрюке построят нефтеналивной терминал

Oil Product Terminal Project for Temryuk Gets Approval

  • The Main Department of State Expertise has approved the project documentation and the engineering survey results for the project to build an oil product terminal in the port of Temtyuk.

    The project is to be developed in three stages. At Stage 1, two berths for light and dark oil products and shore-based infrastructure are to be built. The quay length will make 331.7 m.

    At Stage 2, dredging is planned to develop the terminal basin and navigation aides are to be installed. At Stage 3, additional standers will be added so that the terminal should be capable of handle any sort of oil products.

    The project capacity of the terminal is 2.1 mn tons per annum

    The developer of the project is TemryukMorTrans.


  • Leave a Reply

    Related content
    18.06.2020
    The St. Petersburg branch of the RF Main Department of State Expertise has approved […]
    23.12.2020
    According to the RF Federal Customs Service, Russia’s crude oil export in January-October 2020 […]
    13.05.2020
    Rosneft commenced drilling an exploration well in the West Irkinsky license area, thus the […]
    29.07.2020
    The article is based on SeaNews PORTSTAT online service (available for SeaNews subsribers). Demo […]
    27.02.2020
    According to the RF Federal Customs Service, Russia’s crude oil export in 2019 was […]
    10.06.2020
    Gazprom has reported signing a number of key contracts as part of the large-scale project of the Complex for processing […]
  • Login
  • No Fields Found.