Запущен новый железнодорожный мост через реку Кола

New Rail Bridge in Murmansk Oblast Put into Operation

  • September 28 a new rail bridge over the Kola River in Murmansk Oblast replacing the one that collapsed in June. The construction of the new bridge took just 105 days.

    Unlike the old bridge, the new one has no pillars in the river bed, all the support structures are shore-based. This means the bridge will not affect fish migration and will not be affected by floods, which was the reason of the destruction of the old bridge.

    The bridge consists of three spans, the central one measuring 111.2 meters and the side ones 18.2 meters each. The full length of the bridge is 158.2 meters.

    The bridge will be equipped with a monitoring system that will alert on possible flaws in the bridge structure in real time and automatically suspending traffic across the bridge. This will be the first system of the kind to be implemented on rail bridges in Russia.

    The first train that passed the bridge after it was inaugurated was a freight one. 


  • Leave a Reply

    Related content
    22.06.2020
    On June 19, the first cargo train ran on the rail bypass connecting Murmansk […]
    09.12.2020
    A new Vityaz portal crane has been delivered to Murmansk Commercial Sea Port. The […]
    22.09.2020
    Murmansk Commercial Sea Port has acquired two mobile GIPOREC R130 C machines under the […]
    17.11.2020
    Murmansk Commercial Sea Port has loaded 39,000 tons of crushed stone on board the […]
    04.06.2020
    As of June 3, Murmansk Commercial Sea Port had to direct more than ten […]
    07.12.2020
    Sea Terminal Tuloma has been registered as a fourth resident of the Arctic Capital […]
  • Login
  • No Fields Found.