  • Dredging has started in the Utrenniy LNG and condensed gas terminal basin in the port of Sabetta, Rosatom said in a statement.

    Some 12 mn cubic meters of soil is to be dredged in 2020. The work has to be done in a very short period as the ice-free period in the Arctic area is just 60-70 days a year.

    The terminal construction is to be completed in 2022. The overall dredging volume exceeds 20mn cubic meters.


  • Leave a Reply

    Related content
    20.11.2020
    A steel cutting ceremony marking the start of the construction of the pilot LNG […]
    15.06.2020
    Sakhalin Energy has commenced a complex planned turnaround of its gas production assets. This […]
    23.09.2020
    According to the RF Federal Customs Service, Russia’s crude oil export in January-July 2020 […]
    28.04.2020
    According to the RF Federal Customs Service, Russia’s crude oil export in January-February 2020 […]
    20.04.2020
    The Government of Russia issued an order adding a project for construction of a […]
    04.06.2020
    The Main Department of State Expertise of Russia has approved of the design and […]
  • Login
  • No Fields Found.