TransSiberian Railway Fully Operable Both Ways

  • On July 27 Oleg Belozerov, CEO and Chairman of the Russian Railways Board, reopened train movement on the two-track railway line, part of the TransSiberian Railway that was damaged by a flood.

    ‘The water in the small river rose almost three meters and damaged a pylon of the bridge. The climate is changing, the river has changed its course, which has resulted in the emergency. Preliminarily we estimated it would take 2.5 days to restore one track and 5 days the other one to fully resume operations. In fact, the repair works were completed almost 1.5 day earlier than planned. Train movements has been resumed, and we start sending the trains that had to be delayed. People were working day and night to repair the bridge,’ Belozerov commented.

    He said a new bridge will be built to provide a reliable long-term solution. The new bridge is expected to be constructed within 6-9 months.


  • Leave a Reply

    Related content
    26.07.2021
    On June 25, freight trains started running via the bridge over the Areda River […]
    07.09.2021
    During January-August 2021, Russian Railways loaded 849.8 mn tons of cargo, up 4% year-on-year. […]
    07.06.2021
    Russian Railways and FESCO Transportation Group have concluded an agreement on cooperation in implementing […]
    03.08.2021
    During January-July 2021, Russian Railways loaded 740.7 mn tons of cargo, up 4.5% year-on-year. […]
    16.09.2021
    RZD Logistics, a subsidiary of Russian Railways, and Japan’s Nissin Corporation have signed a […]
    18.05.2021
    According to Russian Railways, the loading of cargo designated for export via Russian sea […]
  • Login
  • No Fields Found.