Первый этап строительства LUGAPORT завершен

First stage of LUGAPORT construction in Ust-Luga Completed

  • Novotrans has announced completing the first stage of the construction of LUGAPORT universal terminal in Ust-Luga. The investment at the first stage exceeded 7 bn rubles ($102 mn). At this stage, artificial territories were built.

    Some twenty vessels were deployed during this stage, including platforms, a floating crane, tugboats and barges. Ver

    Первый этап строительства LUGAPORT завершен cbm of sand and 27 thousand cbm of stone was brought to the site to build the artificial territories.

    The new territory is over 43 ha measuring 1.25 thousand meters long and 350 meters wide. The overall area of the terminal will make 73 ha.

    The universal terminal will handle general cargo, solid bulk, grain and food products serving Panamax, New-Panamax, and Baby-Capesize vessels with a draft up to 15.5 meters.

    The facility will be also capable of handling up to 1.1 thousand railcars a day.

    The total investment into the project amounts to 46.5 bn rubles ($677.7 mn) including 38 bn rubles ($553.8 mn) of Novotrans’ money.


  • Leave a Reply

    Related content
    10.08.2020
    Dredging has started in the Utrenniy LNG and condensed gas terminal basin in the […]
    07.12.2020
    Sea Terminal Tuloma has been registered as a fourth resident of the Arctic Capital […]
    09.12.2020
    After the growth of the Baltic Dry Index last week, it has now started […]
    25.06.2020
    Oboronlogistics, the owner and operator of the “Ambal” ferry deployed between the ports of […]
    16.09.2020
    The situation in the Baltic large-tonnage bulker market on week 37 was unstable. Despite […]
    06.02.2020
    APM Terminals Poti has presented its plans for the creation of a deep-water port […]
  • Login
  • No Fields Found.