Первый этап строительства LUGAPORT завершен

First stage of LUGAPORT construction in Ust-Luga Completed

  • Novotrans has announced completing the first stage of the construction of LUGAPORT universal terminal in Ust-Luga. The investment at the first stage exceeded 7 bn rubles ($102 mn). At this stage, artificial territories were built.

    Some twenty vessels were deployed during this stage, including platforms, a floating crane, tugboats and barges. Ver

    Первый этап строительства LUGAPORT завершен cbm of sand and 27 thousand cbm of stone was brought to the site to build the artificial territories.

    The new territory is over 43 ha measuring 1.25 thousand meters long and 350 meters wide. The overall area of the terminal will make 73 ha.

    The universal terminal will handle general cargo, solid bulk, grain and food products serving Panamax, New-Panamax, and Baby-Capesize vessels with a draft up to 15.5 meters.

    The facility will be also capable of handling up to 1.1 thousand railcars a day.

    The total investment into the project amounts to 46.5 bn rubles ($677.7 mn) including 38 bn rubles ($553.8 mn) of Novotrans’ money.


  • Leave a Reply

    Related content
    28.05.2020
    Gazprom Gazenergoset Geliy is developing an investment project aimed to establish a helium container […]
    14.05.2020
    Acting Prime Minister of the Russian Federation Andrey Belousov has signed a decree establishing […]
    10.04.2020
    Novotrans has loaded the first shipment of grain via the ferry terminal at Ust-Luga. […]
    12.05.2020
    Novotrans Stevedoring Company has loaded the first shipment of sunflower meal from the rail […]
    10.12.2020
    TransContainer has completed a large-scale modernization programme at its Khabarovsk-2 container terminal in Khabarovsk […]
    30.03.2020
    Artur Sedov has been appointed Managing Director of Rostermnalugol, a major coal terminal in […]
  • Login
  • No Fields Found.