«ЕвроХим» построит терминал в Усть-Луге к 2022 году

Mineral Fertilizers Terminal Project in Ust-Luga Approved

  • The St. Petersburg branch of the RF Main Department of State Expertise has approved the design and estimate documents for the mineral fertilizers terminal in Ust-Luga. The project was initiated by EuroChem, a major fertilizers producer in Russia.

    The new terminal is aimed for loading export designated fertilizers stuffed in special purpose containers from railcars onto vessels, and unloading imported bulk fertilizers from sea-going vessels onto rail.

    The terminal to be built in the northwestern part of Ust-Luga Port is to be developed in three phases. The planned capacity on completing all the three stages is 6.025 mn tons per annum and the target throughput is 5.55 mn tons per annum.

    The first phase envisages the construction of Birth 1, railway infrastructure and open warehousing facilities. During phase 2, Birth2 and a roofed warehouse are to be built and the railway infrastructure expanded. The final  third phase envisages the construction of another roofed warehouse and a conveyor system.

    The project completion is scheduled for 2022.


  • Leave a Reply

    Related content
    08.10.2020
    The article is based on SeaNews PORTSTAT online service (available for SeaNews subsribers). Demo […]
    16.06.2020
    Novotrans has announced completing the first stage of the construction of LUGAPORT universal terminal […]
    14.09.2020
    Last week, an investment agreement was signed on the Ryazan Dry Port project between […]
    14.05.2020
    Acting Prime Minister of the Russian Federation Andrey Belousov has signed a decree establishing […]
    27.05.2020
    According to the RF Federal Customs Service’s statistics, in January-March 2020 Russia exported 3.08 […]
    17.06.2020
    According to the RF Federal Customs Service’s statistics, in January-April 2020 Russia exported 3.9 […]
  • Login
  • No Fields Found.