«Звезда» начала третий Aframax

Zvezda Starts Building Third Aframax

  • Zvezda Shipyard in the Russian Far East has started cutting steel for a third 114,000 dwt Aframax tanker. The ceremony was attended by representatives of Rosnefteflot, State Transport Leasing Company, and the Russian Maritime Register of Shipping.

    The series consists of 12 sisterships. The keel-laying of the lead vessel was held in the outfitting slipway on September 11, 2018, during the visit of RF President Vladimir Putin to Zvezda Shipyard.

    At present, sections for the first two vessels are being manufactured and assembled in the workshops and in the slipway of Zvezda.

    The lead ship is scheduled for delivery in 2020.

    The vessels are 250 m long, 44 m broad and have a deadweight of 114 thousand tons. They feature a helipad.

     

     

     


  • Leave a Reply

    Related content
    25.12.2019
    Krasnye Barrikady Shipyard has resumed operations after being conserved for two years. The yard […]
    02.09.2019
    The 15 LNG tankers to carry liquefied natural gas from Arctic LNG 2 project […]
    19.09.2019
    Zvezda Shipyard has laid the keel for a third Aframax tanker ordered by Rosnefteflot, […]
    05.02.2019
    VEB.RF will finance the construction of three new tankers for Novatek. As Igor Shuvalov, […]
    05.11.2019
    SCF Group and VEB.RF Group, a Russian financial institution, have signed an agreement for […]
    27.08.2019
    August 26 Sovcomflot’s Aframax tanker “Korolev Prospect” set sail along the Northern Sea Route […]